Description

EPC stands for Engineering, Procurement and Construction. Power Generation Division is extensively involved in the engineering, procurement and construction (EPC) of the power plants on turnkey basis. A customer who wants only to invest money giving all the responsibilities to other company to build and commission the power plant are served with the EPC works.

EPC contract by BPDB for setting up two HFO fired power plants (100 MW in Gopalganj & 50 MW in Faridpur).

Being the first ever local company, Energypac had been awarded with EPC (Engineering, Procurement & construction) contract by BPDB for setting up two HFO (Heavy Furnace Oil) fired power plants (100 MW in Gopalganj & 50 MW in Faridpur) through international bidding. On 31st December 2011, Honorable Prime Minister, Sheikh Hasina inaugurated the 108.95 MW power plant at Gopalgonj unveiling the curtain on stone in Sheikh Kamal Stadium, Goplagonj at 3.00pm.

With the implementation duration of 450 days, the Gopalgonj power plant was commissioned on 29th August 2011. The plant has started its commercial production on 16th November, 2011. Mr. Rezwanul Kabeer, Director, Energypac Power Generation Ltd. presented the project model to Honorable Prime Minister.

Back to Top